Site Progress this week:

Steel and Formwork for House 3 (Stairs) completed.

Poured Level 1 slab for House 3 / 4, including Denzel walls, stairs and columns.

Surveyor marked Level 2 of House 3 / 4 and piles for House 1 / 2 and sideway walk.

House 1 / 2 cut back commenced (increased height of ground RL).

Piling machine and piles delivered for House 1 / 2 and sideway walk.

Programmed works:

Commence Level 2 Denzel dividing wall of House 3 / 4.

Commence piling for House 1 / 2 and sideway walk.

Prepare and dig footings for House 1 / 2 ground slab.

Plumbers / Electricians rough in drainage on House 1 / 2.

Commenced Level 2 carpentry and timber delivery on House 3 / 4.

 
 